Government Procurement Information Announcement of the Ministry of Finance of the People's Republic of China (No. 970)

来源: 中国政府采购网打印15:38, December 05, 2019 Source: China Government Procurement Network [ Print ]

1 9 号)的相关规定,现将本机关对 政府采购管理系统 —政府采购交易管理运行维护项目 2019-2020 (以下称本项目,项目编号: ZC19TDC19 投诉案作出的处理决定公告如下: In accordance with the relevant provisions of the "Administrative Measures for the Procurement of Government Procurement Information" (Order of the Ministry of Finance No. 19), this agency will now implement the " government procurement management system -government procurement transaction management operation and maintenance project ( 2019-2020 ) " Project, project number: ZC19TDC19 ) The announcement of the handling decision made in the complaint case is as follows:

I. Names of related parties
北京奥维云翼科技有限公司 (以下称投诉人) Complainant: Beijing Aowei Yunyi Technology Co., Ltd. (hereinafter referred to as the complainant)

北京市朝阳区望京西路 48 号院 7 号楼 2 201 Address : 201, 2nd Floor, Building 7, No. 48 Wangjing West Road , Chaoyang District, Beijing

1 财政部信息网络中心(以下称采购人) Respondent 1 : Information Network Center of the Ministry of Finance (hereinafter referred to as the purchaser)

北京市丰台区西四环南路 27 Address : 27 Xisihuan South Road , Fengtai District, Beijing

2 中招政采(北京)咨询有限公司(以下称代理机构) Respondent 2 : Zhongzhao Zhengcai (Beijing) Consulting Co., Ltd. (hereinafter referred to as the agency)

北京市海淀区什坊院 6 号京都信苑饭店 7001 Address : Room 7001 , Kyoto Xinyuan Hotel, No. 6 Shifangyuan, Haidian District, Beijing

Second, the basic situation

代理机构 就本项目作出的质疑答复不满,向本机关提起投诉。 The complainant complained to the agency because he was dissatisfied with the agency's replies to the question. : 1. 本项目需求不明确。 The complaints are : 1. The project needs are unclear. 招标文件对运维团队的要求不合理。 2. The bidding documents have unreasonable requirements on the operation and maintenance team. 3. The qualification required in the bidding documents is not directly related to the needs of the project, and it is suspected of discriminatory treatment. 4. The review factors are not detailed and quantified, and the setting of the score interval is not reasonable. This organ investigates and makes a decision in accordance with the law.

Processing results

第二十九条第(二)项 规定,投诉事项 2 3 缺乏事实依据 According to Article 31 (2) of the "Measures for Questioning and Complaints about Government Procurement" (Order of the Ministry of Finance No. 94 ), the complaints 1 and 4 were established and the purchaser was ordered to resume procurement activities; According to Article (2) , the complaints 2 and 3 lack factual basis .

12 5 December 5 , 2019